Term 1, 2010
|
Project starts |
Week 1, Friday, 5th February |
| Registration and introductions | Week 2, Friday, 12th February |
|
|
|
|
Research fauna, flora and fungi found |
Week 4 Friday, 26th February |
|
Quadrat enhancement plan design started |
Week 5, Monday, 1st March |
|
Quadrat enhancement plans finished and plans put online |
Week 7, by Friday 19th March |
|
Expert feedback on enhancement plans and certificates |
Week 8, Monday, 22nd March |
|
Re-work enhancement plans in light of feedback. Plans put online |
Holidays |
Old timetable
|
Project starts |
Week 1, Friday, 5th February |
|
Registration and introductions Audit and collation of findings completed |
Week 2, Friday, 12th February Week 3, Friday, 19th February |
|
Research fauna, flora and fungi found |
Week 4 Friday, 26th February |
|
Quadrat enhancement plan design started |
Week 5, Monday, 1st March |
|
Quadrat enhancement plans finished Plans put online |
Week 6, Wednesday, 10th March |
|
Expert feedback on enhancement plans |
Week 7, Wednesday, 17th March |
|
Re-work enhancement plans in light of feedback. Plans put online |
Week 8, Monday, 22nd March |
|
Final feedback and certificates |
Week 9, Monday, 29th March |